KPI for Measuring of TAKT Time posted in category Manufacturing
KPI details:
This indicator is for measuring the time between units of production output and customer demand. It is calculated by dividing the available production time per given time period (day, month) by the customer demand per that given time period.
For example, if a bakery works 480 minutes a day and the customers demand is of 100 pieces of bread per day, the Takt Time is 4.8 minutes. Hence, the bakery has 4.8 minutes to make one piece of bread.
It is very important that production and demand are synchronized, and the Takt Time KPI lays at the foundation of a lean production system. Therefore, companies may put in place strategies and systems to ensure that production and demand are matched.
Formula:
Available production time per time period (day, month)/ customer demand per time period (day, month)
KPI Unit: time
KPI Time Frame: update quarterly or annually
Posted by Oana Boteanu | Help to protect community: Flag for moderation
Ideas suggested by WinningKPI community:
Here are comments:
TAKT Time is a very useful KPI to measure timing between production and demand.
Let’s take for example McDonald's.
Let us assume that for one of the McDonald's restaurants, there are 800 customers, demanding one burger each.
The restaurant works 600 minutes a day (10h).
The TAKT Time is:
600/800 = 0.75 minutes per burger
This seems like an impossible equation, however, the restaurant will probably have around 7+ workers
Assuming 7 hours for every hour of shift (regardless of whether they change shifts or not)
Working time: 600 x 7 = 42000
TAKT TIME per worker:
42 000 / 800 = 5.25 minutes per worker per burger
This could also been calculated by multiplying the initial TAKT TIME 0.75 by 7 staff members
Oana Boteanu | September 13, 2012 at 9:53 am
Articles in Manufacturing category:
Relevant articles:
Manage your KPIs with BSC Designer softwareRandom KPI requests:
- KPI for: Measuring of Projected vs. actual hospital bed occupancy -- This indicator is for measuring the diff... 1 comment - add ideas!
- KPI for: Measuring of Deviation of planned budget -- This indicator is for measuring the devi... 1 comment - add ideas!
- KPI for: Measuring of Software Volume and Value -- This indicator is for measuring of Presa... 1 comment - add ideas!
- KPI for: Measuring of audits made by Auditors -- This indicator is for measuring of Audit... 1 comment - add ideas!
- KPI for: Measuring of Revenue per Available Room (Revpar) -- Details: This indicator is for measurin... 1 comment - add ideas!